Upgrading from IBM i 7.4 to 7.5 is not the kind of project that rewards improvisation. The shops that sail through upgrades start their pre-work eight to twelve weeks out — not the ones that scheduled a weekend and hoped for the best. This checklist distills what Paragon’s IBM i consultants have learned across more than two decades of OS upgrades.
Phase 1: Environment Assessment (8–10 Weeks Before)
Hardware Compatibility
IBM i 7.5 requires Power9 or newer hardware. If you’re running Power8 or earlier, the OS upgrade conversation becomes a hardware refresh conversation first. Check your system model before anything else.
- Run
DSPSFWRSCto confirm your current hardware model and OS level - Power8 systems cannot run 7.5 — a hardware refresh is required first
- Verify available disk space: IBM recommends at least 15% free on the system ASP before upgrade
PTF Currency
Your 7.4 system must be at a minimum PTF level before the upgrade. IBM’s upgrade path requires specific cumulative PTF levels to ensure the upgrade process itself runs cleanly.
- Apply the most recent Cumulative PTF package for 7.4
- Apply Group PTFs for DB2, Java, and HTTP server
- Run
GO PTFoption 7 to review PTF status - Resolve any PTFs marked as requiring a delayed apply before upgrade weekend
Common mistake: Shops that skip PTF currency on 7.4 before upgrading frequently hit upgrade failures mid-process. IBM’s upgrade utility expects a certain baseline — if you’re not current, you’ll find out at the worst possible time.
Phase 2: Third-Party Software Audit (6–8 Weeks Before)
Every piece of third-party software on your system — ERP, reporting tools, communications software, security products — needs to be evaluated for 7.5 compatibility. This is where most unpleasant surprises live.
- Generate a complete list of installed licensed programs with
DSPSFWRSC *LICPGM - Contact each vendor and request their 7.5 compatibility matrix
- Flag any products with no 7.5-compatible version — these become blockers or planned exceptions
- Check IFS-based applications separately; Java and Node.js workloads have runtime dependencies that change between OS levels
Pay particular attention to security and compliance software — IBM i access control products often have OS-specific builds that require upgrade coordination with the vendor.
Phase 3: Application Testing Plan (4–6 Weeks Before)
The most rigorous shops restore a production backup to a separate LPAR, upgrade that environment to 7.5, and run structured application testing before touching production. Your testing script should cover at minimum:
- Critical batch jobs — run your top 10 batch processes end-to-end in the test environment
- User access and authority — validate that user profiles and adopted authority function as expected
- Interfaces and integrations — test every system-to-system connection, including EDI translators and ERP integrations
- Output and printing — spool file handling occasionally behaves differently across OS levels
- Performance baseline — run a representative workload and compare metrics to your 7.4 baseline
Phase 4: Upgrade Weekend Preparation
- Full system save to tape or offsite storage immediately before the upgrade begins
- Documented rollback procedure — know how you get back to 7.4 if something goes wrong
- Vendor support contacts on standby for any third-party products that showed issues in testing
- Communication plan for end users on expected downtime window
- Post-upgrade validation checklist — specific jobs and transactions to run before declaring success
The Five Post-Upgrade Tests
Before bringing users back online, run these five checks every time:
- Sign on as a standard user — not a security officer — and verify basic navigation and job submission work
- Run a production order through your ERP — end to end, from entry to posting
- Confirm EDI connectivity — send a test transaction through your EDI translator and verify receipt
- Verify scheduled job queue — confirm your automated job schedule is active and jobs are running
- Check system performance metrics — CPU, memory, and disk I/O should be in expected ranges within 30 minutes of startup
An IBM i upgrade done right is a non-event. The shops that treat it as such — with structured planning, thorough testing, and documented procedures — consistently complete upgrades on schedule with minimal user impact. Those that improvise find out exactly where their preparation gaps were.
Key Takeaways
- Start pre-work eight to twelve weeks out — the upgrades that go badly are the ones scheduled as a weekend.
- IBM i 7.5 requires Power9 or newer, so on Power8 the OS conversation becomes a hardware conversation first.
- Get current on 7.4 cumulative and Group PTFs before upgrading; IBM’s utility expects a baseline.
- Third-party software compatibility is where most surprises hide — request a 7.5 matrix from every vendor.
- Test by restoring production to a separate LPAR, and run the five post-upgrade checks before users return.